Which project management technique focuses on minimizing delays by rearranging project activity execution?

  1. Crashing the schedule

  2. Fast tracking

  3. Resource leveling

  4. Scope creep management

The correct answer is: Fast tracking

Fast tracking is a project management technique that aims to minimize delays by reorganizing the sequence of project activities so that certain tasks that would normally be done sequentially are instead performed in parallel. This technique is particularly valuable when a project is at risk of falling behind schedule, as it allows for a more efficient use of time by overlapping activities. In fast tracking, project managers analyze the project's critical path and look for opportunities to execute tasks simultaneously or to rearrange the tasks' order without affecting the overall outcome. This approach can significantly reduce project timelines, although it may increase risk since overlapping tasks can lead to resource conflicts or increased complexity. While crashing the schedule, resource leveling, and managing scope creep are also important concepts in project management, they serve different purposes. Crashing focuses specifically on allocating additional resources to complete tasks faster, resource leveling addresses the distribution of resources over time to avoid overloading, and scope creep management involves controlling changes to the project scope to prevent project delays or resource overextension.